Exposed Fake Contracts Awarded By Former Governor Jang  As Released By Commission Of Inquiry

3 128

Yakubu Busari

Whatever else may be said about his reign, what cannot be taken away from him was that he tribalised power, familiarized power and corrupted power.  He used the state instrument for private interest. While he reigned, countless Plateau people lost their jobs, positions and opportunity for progression because they offended his tribesmen and women. He welded so much power, he forgot he was in fact elected and did not believe it will ever end. He messed up our state. But perhaps it is in the area of the award of contracts that this bizarre and the 1970s style of use and abuse of power was evident.

What you are about to read in the Ministry of Works is indeed a tip of the Iceberg. In the Ministry of Housing and Urban Development, it was even worse. There he killed the contract award system, suppressed the budgeting system of all other ministries and handed it over to the Ministry of Housing and Urban Development purely for self-enrichment. Hospitals, Zaria Road stadium, Secondary schools, urban and the 5km roads in 17 LGC headquarters were undertaken by the ministry.

Other commissioners, directors and permanent secretaries watched in utter disbelief. The chap there than connived with a scion of the family to pillage and fleas this state and left a carcass of a state. Most painfully even when they renovated houses, because they were bush men without a sense of aesthetics, they permanently destroyed important monuments of the state and disfigured them forever. Guest House no 2 off Rayfield-Zaramaganda road where he named after himself is a typical example. How a government can distort such important historical listed building is unbelievable. To add salt to injury they have even illegally fenced the parking lot directly opposite the gate.

Sen. Jang is said to be good at road projects. What is frightening is the cost of these roads, the quality of these roads and the location of such roads. What is sickening is that the Ministry of Works does not essentially design the roads and bridges; they are done by the contractor, since that was the case, why then did he engage consultants? Added to that, some road resurfacing contracts were awarded at a cost far above the cost for new road contracts. The standard in the country is maximum of 50 million per kilometer for completely new roads (earth works, stone base, gravel, nylon tar etc.

Many contracts were varied without justification. There were also a lot of abuses of discretion. No standard in doing anything in the Ministry. Many roads have since failed substantially (some even when work was still on going) because of poor earth work and no stone base. There is also poor conception of infrastructure and value for money. With all the noise, Jibam Bridge is a single lane bridge. He could have simply dualised it with minimal cost increase. Government now has to again construct another lane as a fresh contract. There are several  gross exaggeration of kilometers of roads awarded (10.59km for new Government House Roads for instance, where the entire roads in the new Government House cannot be more than 4 kilometers) There is also the centralization of payment in the Ministry of Finance, as a result Ministry of Works could not keep track of payment to contractors. There are issue on conflict of outstanding balance, between Ministry of Works and Finance in several cases. No guideline on contract pricing.  Contracts are terminated and no effort was made to recover monies from initial contactor (JUTH Road for instance). He was notorious for awarding new road contracts when the old ones have not been completed. The list goes on and on.

The breakdown below speaks for itself.

Terminus Roundabout to Bauchi road, Dualization of polo Roundabout to Farin Gada. Rukuba Road Satelit Market to Rock Haven Road Network, Gada Biyu flyover  the length of roads is 24.4km;  Total contract sum cost N2,777,121,122.48; amount paid to contractor N2,709,494,765.26; cost per kilometer  for road N115,713,380.10. Contractor: PW Nig. Ltd,

Bukuru Shen-Anguwan Doki- Zawan-Du Loop(Phase II) and Anguldi- Zawan Road the length of roads is 25.65km; total contract sum cost N1,269,756,721.80, amount paid to contractor N1,262,547,658.12; cost per kilometer for road N49,503,186.03. Contractor: PW Nig. Ltd

Construction of Gada Biyu (Kuru)-Forom Road, the length of roads is 10km; total contract sum cost N315,000,000.00; amount paid to contractor N314,000,457.91; cost per kilometer N31,500,000. Contractor: PW Nig. Ltd.

Dualization of Mararaban Jamaa-Heipang Road; the length of roads is 12km; total contract sum cost N2,045,197,182.75; amount paid to contractor N2,020,740,292.91; cost per kilometer for road  N168,395,024.40.  Contractor: PW Nig. Ltd.

Dengi- Wase road; the length of road is 34km; total contract sum cost N1,500,524,010.00; amount paid to contractor N2,493,363,564.45; cost per kilometer for road N73,334.22. Contractor: Foundation Solid Nig. Ltd.

Shendam-Kalong-Shimakar road (Phase 1); the length of road is 21.3km; total contract sum cost N749,349,638.89; amount paid to contractor N740,912,532.78; cost per kilometer for road N34,853,471.58. Contractor: Rick Rock Const. Co. Ltd.

Zamko Mabudi road with spur to Mban; the length of road is 38km; total contract sum cost N1,402,598,665.16; amount paid to contractor N1,402,588,421.18; cost per kilometer for road N36,910,254.35.   Contractor: E E C. International Co. Ltd.

Dokan  Tofsa-Baap Road; the length of road is 25km; the total contract sum cost N1,788,978,691.15; amount paid to contractor N1,788,948,800.14; cost per kilometer for road N71,559,147.65. Contractor: E E C. International Co. Ltd.

Erosion Control and Construction of a Box Culvert at Y Cement Rikkos; total contract sum cost N39,535,650.00; amount paid to contractor N38,910,967.81. Contractor: Alsar Nig. Ltd.

Erosion Control Construction of Retaining Wall and access to Long Gomei close.; total contract sum cost N287,655,810.50; amount paid to contractor N287,767,148.00. Contractor: Moulds Nig. Ltd.

River Jibam Bridge and access road to Chip Village including Jibam-Dokan Kasuwa Road and Kwa; length of road is 18km; the total contract sum cost N1,608,961,767.29; amount paid to contractor N1,509,567,454.91; cost per kilometer for road N89,386,764.85. Contractor: E E C. International Co. Ltd.

Construction of Washout Section of Gumshar Bridge; total contract sum cost N30,102,364.50; amount paid to contractor N29,324,457.65. Contractor: Sebatech Nig. International.

Construction of Washout section on Bapkwai Bridge approaches along Langtang-Garkawa road in Langtang North LGA; total contract sum cost N6,500,000.00; amount paid to contract N6,373,799.60. Contractor: BILMORE Co. Ltd.

Construction of Washout on Mban Bridge approaches; total contract sum cost N4,711,925.00; amount paid to contractor N4,391,248,98. Contractor: ATM Nig. Ltd.,

Construction of Washout Section area on Tonzong Barley Bridge Gindiri in Mangu LGA; total contract sum cost N2,109,591.45; amount paid to contractor N1,895,471.00. Contractor: Rick Rock Construction Nig. Ltd.

Dualization of Plateau Specialist Hospital Roundabout-Hill Station junction (Resurfacing), Hill Station Junction- Polo Roundabout (J.D Gwomwalk Way), Zaria road  Busa Buji; Laranto- Katako road, CBN- Land and Survey road resurfacing; length of road is 16.35km,  total contract sum cost N2,832,154.018.13; amount paid to contractor N2, 662,607,806.92; cost per kilometer for road N173,220429.24. Contractor: PW Nig. Ltd.

Construction of:- a.  Gut- Rayfield, 7.5Km, b.  Lati-SHEN BY 6.0km, c.  Shen-Kwang-Rayfield 10.31km, d.  Du-Shen Road Network4.29km, e.  Du-Bisichi Kuru Road with Spur to Madu 8.81km, f.   Heipang- Kuru 6.8km, g.  ECWA farm- Shen Kwang road  5.3km, h. TCNN road 2.2km, i.   Rayfield Golf course-Shen Kwang road 3.8km, j.  Rayfield-Gura Topp 2.85km; length of roads is 57.91km; the total contract sum cost N4,806,767,836.99; amount paid to contractor N4,182,903,024.89, cost per kilometer for road N83,004,107.01. Contractor: PW Nig. Ltd.

Construction of Bukuru Lowcost  Rantya Gyel Road, length of road is 16km; total contract sum cost N1,460,824,524.11; amount paid to contractor N1,418,353,842.21; cost per kilometer for road N91,301,532.76. Contractor: Jodalsam Nig. Ltd.

Bisichi korot-Fan-Rite-Mangu Halle with Spur to Heipang, Kwi, Nding-Kassa an Rawuru., length of road is 70km; total contract sum cost N5,303,476,304.29; amount paid to contractor N2,660,566,843.00; cost per kilometer for road N75,763,947.20. Contractor: E E C. International Ltd.

Pankshin- Langkang- Dyis Sihin with Spur to Asa Akong; length of road is 15.5km; total contract sum cost N984,911,796.75; amount paid to contractor N871,071,603.76; cost per kilometer for road N63,542,696.56. Contractor: Foundation Solid (Nig) Ltd.

Construction of Mangu- Gindiri-Lere road with Spur to Tonzong- Chanso and Gindiri school; length of road is 45.5km; total contract sum cost N2,434,143,156.22; amount paid to contractor N1,702,706,433.00, cost per kilometer for road N53,497,651.79. Contractor: Tilley Gyado & Co. Nig Ltd.

Construction of Fobur-Angware Road; length of road is 27km; total contract sum cost N1,433,133,976.50; amount paid to contractor N1,238,010,364.40; cost per kilometer for road N53,079,036.17.  Contractor: Foundation Solid (Nig)Ltd.,

Access road to school of Nursing and Midwifery Vom and Vom Township Road network; length of road is 2.47km; total contract sum cost N166,866,082.50; amount paid to contractor N53,610,225.03; cost per kilometer for road N67,557,118.42. Contractor: Haga Concept Nig Ltd.

Jebbu Bassa-Binchi-Buyo road with Spur to Zagun; length of road is 18km; total contract sum cost N1,392,031,712.30; amount paid to contractor N1,130,622,797.08; cost per kilometer for road N77,335,095.12. Contractor: United Radak Nig. Ltd.

Rukuba- Miago- Farin Lanba Road with Spur to Duchai and School of Accountancy; the length of road is 50km; total contract sum cost N3,200,982,399.90; amount paid to contractor N2,124,479,985.00; cost per kilometer for road N64,019,647.100. Contractor: Rick Rock Nig. Ltd.

Tahos- Rim Bachit-Shinung- Jol-Gashish; the length of road is 50km; total contract sum cost N4,996,524,229.51; amount paid to contractor N2,556,251,028.00; cost per kilometer for road N99,930,484.59. Contractor: Rick Rock Nig Ltd.

Jengre-Amo Maikatako- Karambana; the length of road is 26km; total contract sum cost N2,602,868.83; amount paid to contractor N1,296,480,466,75; cost per kilometer for road N100,095,225.72. Contractor: United Radak Nig. Ltd.

Mangu  Bwai- Mushu Road; the length of road is 17km; total contract sum cost N1036,652,939.44; amount paid to contractor N688,842,130.21; cost per kilometer for road N60,979,537.07. Contractor: Salta Nig. Ltd.

Zarmaganda  Mazaram road Network and Spurs; the length of road is 10.04km; total contract sum cost N1,217,833,617.51; amount paid to contractor N623,685,355.68; cost per kilometer for road N121,298,169.07. Contractor: Jodalson Glo Ltd.

Mangu Sabo-Layi Road; the length of road is 6km; total contract sum cost N448,554,628.00; amount paid to contractor N134,563,388.40; cost per kilometer for road N74,759,104.67. Contractor: Cosmos Nig. Ltd.

Dualisation of Lamingo  Juth Road; the length of road 8km; total contract sum cost N3798,472,467.64; amount paid to contractor N3,647,800,134.74; cost per kilometer for road N474,809,058.45. Contractor: PW Nig. Ltd.

Dualization of Gada Biyu-Rukubu Road mkt Kabong Road Network; the length of road is 6km; total contract sum cost N1,081,332,348.11; amount paid to contractor N876,759,037.53; cost per kilometer for road N180,222,058.01. Contractor: PW. Nig. Ltd.

Rayfield Latiya Doi Dyemburuk road; the length of road is 30km; total contract sum cost N3,968,812,882.44; amount paid to contractor N876,759,037.53; cost per kilometer for road N180,222,058.01. Contractor: P.W. Nig. Ltd.

Construction of D.B Zang Junction Gyel- Gyero Tanchoi and Tahel road; the length of road is 16km; the total contract sum cost N1,272,820,683.69; amount paid to contractor N897,490,566.93; cost per kilometer for road N79,551,292.73 . Contractor: Foundation solid Nig. Ltd.

Construction of Gunji  Shiwer Dokpai with Spur to Tiplik; the length of road is 33km; the total contract sum cost N2,212,319,314.45; amount paid to contractor N1,929,676,088.07; cost per kilometer for road N67,039,979.22. Contractor: Hajaig Nig. Ltd.

Jos Mazah Angware Road; the length of road is 31km; the total contract sum cost N4,983,002,683.11; amount paid to contractor N1,629,611,657.00; cost per kilometer for road N160,742,022.03, Contractor: EEC International Ltd.

Langtang  Garrkawa  Yelwa Shendam with spur to Lalin; the length of road is 70km; the total contract sum cost N3,900,290,524.74; amount paid to contractor N1,539,210,468.32; cost per kilometer for road N255,718,436.06. Contractor: Retro Nig. Ltd.

Korot Bakin Kogi Kaduna Gindiri road; the length of road is 44km; the total contract sum cost N3,691,534,200.00; amount paid to contractor N1,359,761,741.62; cost per kilometer for road N83,898,504.55. Contractor: Tiley Gyado & Co. Nig. Ltd.

Bukuru and Fwavwel Road Networks in Rayfield and Daulisation of the Bukuru little Rayfield Road with Spur; length of road is 29.35km; total contract sum cost N4,404,187,510.00; amount paid to contractor N3,204,500,050.12; cost per kilometer N150,057,496.08. Contractor: Rick rock Nig. Ltd.

Daulisation of old Airport road  Rayfield  Bukuru with Spur to Giring and Chango Pyang; length of road is 16km; total contract sum cost  N6,339,489,410/00; amount paid to contractor N4,764,491,269.30; cost per kilometer for road N396,218,088.12. Contractor: PW Nig. Ltd.

Flyover at Secretariat junction with slip Road and under passes; length of road is not stated; total contract sum cost N4,694,279,514.78 amount paid to contractor N2,577,291,474.24. Contractor: PW Nig Ltd.

New Government House Road Infrastructure; length of road is 10.59km; total contract sum cost N3,236,325,931.32 amount paid to contractor N3,236,325,931.08; cost per kilometer for road N305,602,070.94. Contractor: PW Nig. Ltd.

Re-surfacing and Reconstruction of Mararaban Jamaa British American junction; the length of road is 22km; total contract sum cost N10,557,641,430.00 amount paid to contract N4,822,430,279.62; cost per kilometer for road N479,892,792.27. Contractor: PW Nig. Ltd.

Mbar-Mangar-Richa Kamwai Road; the length of road is not stated; total contract sum cost N3,266,802,425.25. Contractor: Story  Alyans Const. Ltd.

Construction of Rantya-Gyero Road with Spur to Nyango Gyel; length of road is 7.5km; total contract sum cost N1,226,151,621.87; cost per kilometer for road N163,486,882.91. Contractor: Lojok Nig. Ltd

Road/parking space of New Zaria Road Stadium; length of road is not stated; total contract sum cost N766,302,263.05; amount paid to contractor N241,385,212.86. Contractor:  PW Nig Ltd

HiIl Station Round about to Tudun Wada bridge; length of road 800 meters; total contract sum cost N740,321,821; amount paid to contractor N740,321,821; cost for less than a kilometer N740,321,821.74. Contractor: PW  NIG LTD

Direct Labour Works (completed); length of road is 3.35km; total contract sum cost  N229,591,033.09; amount paid to contractor N229,591,033.09; cost per kilometer for road N65,534,636.74. Contractor: Ministry of work

Rehabilitation of Washout Section on Mban and Bapkwai Bridge; length of road is not stated; total contract sum cost N287,121,229.45; amount paid to contractor N287,121,229.45. Contractor: Ministry of works

Construction of Road Network within some slum areas of Jos South. Length of road is not stated; total contract sum cost N855,376,168.50; amount paid to contractor  N256,612,850.00. Contractor: Erapon Nig Ltd

Construction of Road Network in Bukuru and neighborhood; length of road is not stated; total contract sum cost N3,927,598,008.14; amount paid to contractor N589,139,701.22. Contractor: Rick Rock Ltd

 

 

3 Comments
  1. Timnan says

    Thank you very much sir for taking out time to list just but a few contracts of the past administration. That’s what we call the developmental dividends of democracy and you forgot to mention the fake contracts he awarded… Pls for your information roads are not priced by length alone but length and width all together (I.e by area) you can’t say since Dariye constructed the Bokkos road at #naira, per kilometres the same should be paid for the dual wider Gada Biyu roads with a double drainage system. Thank you sir and may The Good Lord bless Baba Jang

  2. Dng Basam says

    Where are the fake contracts as captioned in the story? The story Teller failed to hide his disdain for Sen Jang by painting him with all unprintable names! This type of reportage is completely unprofessional and averse to clinical investigative journalism. Jang is never a saint. And I do not support any form of mismanagement by any politician but I find it hard to consume these types of ‘blackmail’. We need a forensic analysis of these contracts to be able to provide and inform view. The writer simply succeeded let’s us knw the developmental stride and legacies Jang left behind! Journalism is not madness!

  3. Pankes Dillam says

    The writer has shown his naivety in construction projects. Please where on earth did you get that fact that a standard km of road in nigeria cost 50 million naira. Thats absurd, you have failed to educate the readers that some of these roads are dualized and include culverts, bridges and other ancillary road works. Every road project has it’s own peculiarities as terrains, hydraulic structures required, type of road, topography etc are determinants of the final price. Also your article did not indicate the fake contracts as you opined. And finally does your article potrays the findings of the judicial commision of inquiry? If it does then I must say the JCI was then a wate of taxpayers money