Usman Gur Mohammed
The Concerned Power Sector Stakeholders and Consumer Association (CPSSCA) is calling on President Muhammadu Buhari to immediately dismiss, Usman Gur Mohammed, the interim Managing Director of the Transmission Company of Nigeria, TCN over the multiple instances of systems collapses leading to power outage in several parts of the country.
The group noted that Nigeria had experienced over 30 instances of system collapse within few months with 6 recorded in the month of January 2018. It blamed the collapse as a result of the poor management of system operations under the watch of Mr. Mohammed, who they described as an accountant, without the technical pedigree to manage the specialized power sector operations.
CPSSCA revealed that major transmission lines are tripping almost on a daily basis in recent times which has resulted in total or partial system outages (collapse). Reports on the failure of most of the switch gears (Breakers and Isolators) go unreported by the regions probably out of fear for being accused of sabotage.
“The reason for this unfortunate development is due to negligence of routine maintenance and staff demoralisation. The interim Managing Director who is an accountant has no regards for technical competency of staff thus relegating them to the background,” said Gbenga Suleiman, the group’s spokesperson. He suggested that the current situation assumes a dimension of economic sabotage and wondered if the TCN boss might be a beneficiary of the contracts to repair the damaged assets.
The group in the petition to President Buhari, warned that the continued management of the TCN by Mohammed might lead to total power outage as several power transmission assets have collapsed already.
The petition reads in part, as follows;
“Since he assumed the position of interim managing Director of TCN in February, 2017, the following power transmission assets have either been burnt out or damaged beyond repairs, resulting in partial or total blackout in the affected communities.
Below are the details of power transformers that TCN lost in the past 9months:
with Replacement cost of N850million
Two additional transformers at Nkalagu 45MvA as well as 60Mva 132/33kv at Uyo was recently burnt.
The total replacement costs of these assets amount to N3.85bn with procurement and manufacturing duration of 9 months.
It is on record that the President gave an approval for the interim arrangement for 3 to 6 months, which was unofficially extended to ONE year. We therefore call on Mr. President to direct the immediate termination of Usman Gur Mohammed as the Managing Director of the TCN to save the country from imminent total power blackout in the country,” the group stated.
A delegation from the Abdul Samad Rabiu Africa Initiative (ASR Africa), led by its Managing…
The management of Kogi State Polytechnic, Lokoja, has suspended six lecturers over allegations of unauthorised…
The All Progressives Congress (APC) has constituted a 276-member national campaign council, alongside 12 specialised…
Three Heirs Holdings portfolio companies - Transcorp Group, Abuja Electricity Distribution Company (AEDC) and Redtech…
A 55-year-old businessman, Onuigbo Ndubisi Chinedu who deals in clothing at the popular Balogun market,…
Senator Onyekwere The Chairman of Action Peoples Party (APP) Imo State Chapter, Hon.Chief Ernest Njesi,…
This website uses cookies.